Wednesday 1 May 2013

Prepare for final report.

After the presentation was completed on last week. The next progress that need to be completed is the Final Report. On this week, i really focus to complete my Final report. This Final Year report contain 35% of the carry marks. The presentation contains 35% and the blogs contain 30% of the carry marks. Total up the marks will get 100%. I already done Chapter 1, Chapter 2, Chapter 3, Chapter 4. I will complete my Final Report by next week insyallah.

Thursday 25 April 2013

Presentation day

Today is the presentation day. Im bring my project to the Unikl Bmi to present and demonstrate my project. Below are the picture of me and my friends after the presentation.
Most of the student in this picture are under Miss NorrolHoda from electrical section. We take picture together as a memory for this day.

Thursday 18 April 2013

Poster for industry day

Today i would like to design the poster for the industry day. this poster need to include:
             1. objective
             2. methodology
             3. diagram
             4. application
             5. description
             6. result
             7. reference
After design the poster, this poster need to be printed on A1 size. After design  this poster i print this poster at WAQED,UIA.

Thursday 11 April 2013

Circuit complete

Below are the picture of the complete circuit for control and monitor temperature by scada. This circuit attached at the pail in order to check the current temperature.

Complete Circuit


Thursday 4 April 2013

Finishing the hardware

Today, i would like to assemble the hardware and the circuit. Here i attach the picture that i already completed assembled.

From figure above, the circuit of control and monitor temperature project was put at below of the hardware. It attach at the pail because near to water for the sensor detect the temperature. 

This is the view of the complete project of control and monitor temperature by scada system.

Thursday 28 March 2013

Design Hardware


After buy the wood and the equipment that need to make hardware of this project. the first things that need to is to design the hardware where want to put the item to look like view at hot spring. below are the picture of designing the hardware.
before put the glue. the arrangement need to be done in order to make it look nicely. This hardware is to look like at hot spring because the viewer can easily understand  what this project is all about. 
Completed design of the hardware.


Thursday 14 March 2013

Testing Project

Today i would like to share result of testing of my project. from the figure there are two component that i need to test which is the heater and the water pump. The testing is to ensure that the heater and the water pump can operate when it receive the signal from computer. This test was successfully done  because the heater and the pump can operate as want i wanted.